The start of construction on the Crissy Lake Modification Project has been postponed to Fall 2027 due to a previously unforeseen permitting requirement. Project reviewers determined that the work requires certification under Section 401 of the Clean Water Act, a process that typically takes three to six months to complete. Additional information on this certification...
Read More
The Environmental Assessment Worksheet (EAW) for the Crissy Dam Modifications Project has just been completed and made public by the DNR. The EAW is accessible at Crissy Lake Dam Modifications Project Page. It will now go into a 30 day public review and comment period. Electronic comments can be submitted online here: Online Comments for...